Officials at Scottish Borders Council extended a valuable £300,000-a-year waste recycling contract under delegated powers without inviting competitive tenders even though the existing suppliers demanded a near doubling of their prices at one point during discussions.
Not Just Sheep & Rugby has already reported on the "highly unusual" decision by SBC that their long-standing contract for dealing with 10,500 tonnes of so-called dry mixed recyclates (blue bin rubbish) would continue to be in the hands of J & B Recycling Ltd, of Hartlepool without rival firms having the opportunity to bid because of "special circumstances".
Since 2005 that company which later became sub-contractors to New Earth Solutions - the now dissolved firm chosen by councillors to solve the Borders' waste treatment problems - has handled collections of domestic recyclable rubbish which are hauled 110 miles by road to the J & B Tees-side facility.
One of two so-called transparency notices published by SBC set out to explain why other firms had been denied the chance to bid for the work when J & B's contract expired in March 2017. The notice claimed: "Scottish Borders Council is in the process of reviewing future requirements for all Waste Management Services. During this period the highest priority for the Council is existing service delivery.
"Therefore until the new Waste Management Plan is fully implemented and to avoid a disproportionate impact on current waste operations it is necessary that existing arrangements relating to service provision continue. A detailed options appraisal has been conducted which confirms that this approach is the most appropriate solution delivering best value while meeting the necessary requirements of the Public Contracts (Scotland) Regulations 2015."
Then a second notice gave this reason for the deviation from normal procurement procedures: "Extreme urgency brought about by events unforeseeable for the contracting authority".
Additional details of what led up to the contract extension have now emerged in a heavily redacted (censored) version of an internal council briefing note. The 21-page document was released following a Freedom of Information request, but unfortunately virtually every figure in the report has been hidden from view.
The note records that a firm of consultants had been called in to carry out an appraisal of options available once the contract came to an end.
"The Options Appraisal concluded that extension of the current contract with J&B Recycling Ltd was most likely to achieve the Council’s short-term procurement objectives and achieve the lowest price given the current market conditions. The negotiation with J&B regarding the contract extension progressed well until January 2017 when J&B changed position and requested a significant price increase i.e [redacted figure]."
The Council requested J&B reconsider their position and revisited the other viable options available: J&B subsequently proposed two alternative options with increased risk share but at significantly reduced rates.
On the other hand the Briefing Note warns: "The
main risks of entering into the contract are: 1. The Council is exposed to
additional risks and price fluctuations compared to the current contract. 2.
The Council may receive a challenge during the 10 day standstill process. If
this occurs it will need to go out through a full procurement exercise. This is
likely to result in additional cost whilst the procurement project is
undertaken."
More detailed background to the discussions between SBC and J & B shows how the contractors came to request a sizeable price increase.
On 19th January 2017 J&B’s Commercial Manager confirmed
that they had taken the proposal to their Board and they had indicated that
terms and price did not deliver the required return on investment.
"The main
justifications were as follows: J&B’s paper contract was due to expire and
it was unlikely they would be able to negotiate a fixed price at the level of
their current arrangement. The paper contract was likely to require card to be
extracted and this would need significant additional investment into their
plant. Their haulier had recently lost a back haul contract and
J&B were expecting a price increase.
"It was now clear that the
extension of the current contract with J&B may no longer represent the best
option. The Council outlined to J&B that they were unable to enter into a
contract at [redacted figure] nearly double the current price, and asked them to rethink their
proposal."
However, as reported, the range of possible alternative solutions were assessed, then discarded.
The Briefing Note concludes: "The Council has been put in a difficult position
as a result of J&B changing their position and the fact that the current contract expires at the end of March
2017. Following a review of the
viable options available to the Council, at the 1st March 2017, the following
options are considered to represent
best value in terms of price: 1. New
contract with J&B 2. Partner
with [redacted] Council."
No comments:
Post a Comment