by EWAN LAMB
Conservative-led Scottish Borders Council may have inadvertently set the mood for Philip Hammond's budget by embarking on a borrowing spree which will increase local government debt in the region by in excess of £15 million in 2017/18, equivalent to more than £280,000 a week.
However, this complete turnaround in fiscal policy in the face of Tory declarations stressing 'we must get the deficit down' has not even merited a mention in Borders local newspapers even though the details were published in full in the council's mid-year Treasury Management Report.
The latest hike in borrowing will push SBC's outstanding debt to a figure well above the council's annual revenue budget. The report revealed: "Additional borrowing amounting to £10 million has been undertaken in April 2017. Further borrowing of £5.2 million is anticipated during the remainder of the year".
All of that against a backdrop of £6 million additional grant from the (SNP) Scottish Government and the prospect of the much trumpeted South-east City Deal which is already turning out to be far less attractive for the Borders than the spin doctors would have us believe.
So much for the battle cries of those at the top of the Tory Party since 2010 that "we must not leave higher burdens of debt to our children and grandchildren". Labour were the bad guys who would bankrupt the nation by borrowing billions to fund public services, warned Theresa May and her Cabinet colleagues
In the Borders this greater reliance on borrowing means the council’s external debt which was already £265.4 million at the start of the current financial year (bigger
than the annual revenue budget of £264.7 million) will now rise to £271.2 million.
Apparently the current approved (capital expenditure) budget at SBC is higher than the original budget due to "adverse timing movements from February 2017 to 31 March 2017 in areas of the capital plan".
According to the finance document: "The key drivers for the 2016/17 changes are assets and infrastructure - roads and transport infrastructure total additions to budget amount to £1.86 million.
"Also increases to the Land and Property Infrastructure projects total £0.63 million. The Other Corporate Services budget has increased by £2.85 million, principally from the inclusion of additional £2.64 million ICT Transformation budget.
"Children & Young People - School Estate budget increases amount to £3.32 million. The key increases in estimated expenditure result from a net timing movement relating to the construction of Broomlands (Kelso) and Duns Primary Schools.
"Economic Development - Additional budget as a timing movement between financial year amounting to £3.6 million relates to the Hawick Regeneration project".
The council's liabilities comprise long-term borrowing of £198.3 million plus £72.9 million of other outstanding debts. The level of debt has increased significantly over the last five years. The equivalent figures in 2010/11 were £164.8 million for long term borrowing plus £61.8 million for "other liabilities".
But at least the Tory group on SBC can claim to be in step with the party hierarchy. Following yesterday's UK budget in which Chancellor Hammond also embarked on a campaign to increase borrowing any hopes of balancing the nation's books have been dashed until at least 2031.
Unfortunately, in the Borders case, - given the current direction of travel - it could be several centuries before the debt is paid down, leaving generations of council taxpayers to pick up the tab for servicing those burgeoning external liabilities. Interest payments are currently running at more than £10 million a year.
Thursday, 23 November 2017
Monday, 30 October 2017
Will Borders waste station find favour this time?
DOUG COLLIE on a council dilemma
Just six months after throwing out proposals for a multi-million pound waste transfer station (WTS) at Galashiels Borders councillors will be invited to backtrack and sanction virtually the same scheme when they meet next week.
Members of Scottish Borders Council planning committee turned down an application in April from local authority colleagues for the development of the storage facilities at Easter Langlee amid fears for road safety outlined in objections from local residents.
There were suggestions at the time that councillors were 'playing to the gallery' just a few weeks before municipal elections were held in May.
That decision threw SBC's waste management strategy into complete chaos given the looming deadline for the closure of landfill sites in Scotland. The WTS is required as a matter of urgency so that tens of thousands of tonnes of household refuse can be taken to Easter Langlee before it is transferred by road to treatment facilities elsewhere.
There are even more individual objections (eighteen) to the revised application which will be considered next Monday. But as before, senior planners at SBC are recommending approval even though they concede the serious shortcomings of the C77 road cannot be overcome.
Opponents have the backing of local ward councillor Harry Scott, and a nearby residents' association has also tabled a strong objection.
A 22-page report compiled by planning officer Carlos Clark outlines the pros and cons associated with the siting of the WTS at Easter Langlee.
The report says amenity impacts - according to protesters - include:
*The development will prolong and may exacerbate
noise, dust and smell concerns (including odours during construction); visual
impacts, including trees and landscape issues; vehicle noise (including from more
HGVs and from reversing vehicles); and air pollution.
Just six months after throwing out proposals for a multi-million pound waste transfer station (WTS) at Galashiels Borders councillors will be invited to backtrack and sanction virtually the same scheme when they meet next week.
Members of Scottish Borders Council planning committee turned down an application in April from local authority colleagues for the development of the storage facilities at Easter Langlee amid fears for road safety outlined in objections from local residents.
There were suggestions at the time that councillors were 'playing to the gallery' just a few weeks before municipal elections were held in May.
That decision threw SBC's waste management strategy into complete chaos given the looming deadline for the closure of landfill sites in Scotland. The WTS is required as a matter of urgency so that tens of thousands of tonnes of household refuse can be taken to Easter Langlee before it is transferred by road to treatment facilities elsewhere.
There are even more individual objections (eighteen) to the revised application which will be considered next Monday. But as before, senior planners at SBC are recommending approval even though they concede the serious shortcomings of the C77 road cannot be overcome.
Opponents have the backing of local ward councillor Harry Scott, and a nearby residents' association has also tabled a strong objection.
A 22-page report compiled by planning officer Carlos Clark outlines the pros and cons associated with the siting of the WTS at Easter Langlee.
The report says amenity impacts - according to protesters - include:
*The development will unfortunately prolong use of the site
for waste treatment or disposal. Further consideration should be given to
protecting the area for residential and other compatible uses.
*Concerns are
raised regarding impacts on existing residential properties, and potential for
future houses.
*The content and findings of a Transport Statement produced by the applicants are
challenged, including factual accuracy, speed survey findings and proportion
of commercial vehicles using the road. The report is considered to be one-sided
in favour of the development being approved.
The report adds: "There
is no answer to the fact that the pinch point between Aislinn Cottage and No 2
Easter Langlee Cottages cannot be widened. This is the most dangerous point of
a pedestrian’s journey where the road is not wide enough to accommodate a HGV
and another vehicle passing each other, visibility is severely restricted, and
verges are extremely narrow and overrun by HGVs. The transport statement
confirms that a solution cannot be achieved.
"Another
blind bend creates a similar hazard further north. Proposed improvements were
previously judged to be inadequate. There is no change in the improvement
proposals that can overcome the intrinsic unsuitability of the C77."
The report to councillors also states that all properties flanking the C77 have had vehicles enter
their property through boundary fencing, one experiencing this twice. Vehicles
have also come off the road and fallen into the valley adjacent the waste site.
Photographs demonstrate instances of vehicles involved in accidents, including
one showing a Council refuse lorry (though it is unclear if the lorry was
involved in the accident).
Despite there being a
30 mph limit here, a traffic survey carried out on behalf of the Council
indicated that, on a weekly average, a substantial number (47.1%) exceeded the
speed limit, with excessive speeds ranging between 36.3 mph and 49 mph.
People and children
(sometimes unsupervised) with or without dogs walk this road and walkers are
increasingly using it. Six properties on this stretch have no other means of
accessing a bus stop or post-box without walking on this road. The path through
the industrial estate is steep, on an angle and has steps. Therefore, the only
route for wheelchair users, those with restricted mobility and parents with
pushchairs is to use the C77. There is no footway and the grass verge is
non-existent.
Locals also warn: " A major accident,
with possible fatalities, may occur and the development should be stopped
before the inevitable occurs."
But according to Mr Clark: "The provision of the Waste Transfer Station will
provide clear community benefit, particularly in allowing closure of the
landfill site”.
The Transport Statement states that there would be 6 extra
vehicle movements per day of which 5 would be articulated lorries, when
compared with the existing traffic for the landfill. This amounts to 88
movements per day in total, of which 14 would be artics., as opposed to 82 and 9
for the landfill site respectively.
The predicted traffic would be less than
that for the consented MBT (Mechanical Biological Treatment) facility. While that consent is an historic approval it is,
nonetheless, a consent that is capable of still being implemented without
further planning approval and the judgements leading to that permission are
valid considerations here. This increase in traffic is not considered to be
significant, he writes.
His report concludes: "Ultimately, it must be acknowledged that the development
will replace the existing landfill activity and achieve a waste management
solution that will have less intensive traffic implications than the consented
MBT facility.
"While objectors’ concerns are legitimate and fully
acknowledged, there is insufficient evidence to suggest that the WTS would
result in road safety impacts that are so materially different to either the
existing landfill operations or approved MBT facility such that the C77 would
be incapable of safely accommodating its traffic."
The recommendation is for approval with conditions.
It will be interesting to see whether the reconstituted planning committee sticks with the previous decision or gives the WTS their seal of approval.
Thursday, 26 October 2017
Methane from Borders landfill = 7,000 cows!
Blowing in the wind EXCLUSIVE by EWAN LAMB
The 356,000 kilos of methane sent skywards from the Easter Langlee landfill site on the outskirts of Galashiels in 2016 equates to the annual gas production of 7,120 beef cattle, according to an investigation conducted by Not Just Sheep & Rugby.
The rubbish tip operated by Scottish Borders Council is already mired in controversy as planners consider a second application from the local authority who wish to develop a £4 million waste transfer station on land which may already be contaminated.
A growing number of objections to that plan - mainly on grounds of road safety - have been submitted to the planning department which is, of course, another service run by SBC. In the last few days Councillor Harry Scott, one of the Galashiels representatives on the council, has added his voice to the list of waste transfer station opponents.
Meanwhile the Scottish Environment Protection Agency (SEPA) today published environmental statistics on emissions of greenhouse gases in 2016 including methane and the even more damaging chlorofluorocarbons (CFCs) and hydrochlorofluorocarbons (HCFCs).
The reporting threshold for methane is 10,000 kgs per annum and for CFCs and HCFCs 1 kg per annum.
That means the 356,000 kgs of methane emissions at Easter Langlee last year were more than 35 times above the reporting threshold. There was a slight drop from 403,000 kgs in 2015, but the figure was well above the 2010 level of 274,000 kgs.
Scientists claim methane warms the planet by 86 times as much as carbon dioxide (CO2). And based on the estimate that one beef cow emits 50 kgs of methane into the atmosphere each year it would require 7,120 head of cattle to equal Easter Langlee's "performance".
The toxic mixture of emissions at Easter Langlee also included 27.4 kgs of CFCs and 21.4 kgs of HCFCs. Both figures are more than 20 times above the reporting threshold. Levels of CFCs and HCFCs above the threshold are not generated from any other site in the Scottish Borders.
SBC intends closing the landfill facility down in 2018 in yet another bid to comply with Scottish Government regulations on burying household refuse.But their intentions could be jeopardised if planning committee members reject the waste transfer station concept again.
The waste disposal issue should have been dealt with by 2013 had proposals for a modern Mechanical Biological Treatment (MBT) facility been delivered on time. Instead SBC took a huge gamble in a bid to incorporate untried Advanced Thermal Treatment (ATT) technology into the project which resulted in the entire venture having to be aborted in 2015 without a single brick being laid on site.
Now we wonder - mischievously - whether spreading vast quantities of seaweed over the landfilled sections of the Easter Langlee site might cut methane emissions by say 90%. Apparently boffins in Australia may have come up with proof that including seaweed in the diet of cattle might curb their harmful 'botty burps'.
News of this potentially game changing breakthrough emerged in a Scottish Parliament written answer, published only hours before SEPA produced their data. Here is the riveting exchange in full:
John Scott (Ayr) (Scottish
Conservative and Unionist Party): To ask the Scottish Government what
evaluation it has made of the claim made by the University of Queensland that
including a certain type of seaweed in the diet of cattle can reduce their
methane output by up to 90%.
Fergus Ewing: (Cabinet
Secretary for Rural Economy): The Scottish Government is aware of this work as
part of a wider assessment which it has undertaken on the potential for
reductions in GHG emissions to be made through changes to livestock diets.
John Scott (Ayr) (Scottish
Conservative and Unionist Party): To ask the Scottish Government whether it has
invited any research institutions to evaluate the work of the University of
Queensland with regard to methane reduction in cattle by including seaweed in
their diet, and to assess whether a Scottish application might be found for this
research.
Fergus Ewing: Experts at
Scotland’s Rural College were invited to consider these findings and advised
that the reductions observed were based on laboratory based tests only, using
seaweeds which are not native to Scottish waters. We remain keen to see how this
research progresses and shall continue to monitor developments in this emerging
research area.
Tuesday, 24 October 2017
Council "scandal" hits the headlines
NOT JUST SHEEP & RUGBY reproduces the text of an article which appeared in today's edition of Scotland's The National newspaper. It is the first time a daily paper has covered the dossier of evidence compiled after Scottish Borders Council poured at least £2.4 million of public money down the proverbial drain on a worthless infrastructure project
Bombshell
report reveals fresh concerns over aborted waste project that cost council
taxpayers £2.4m
by Martin
Hannan
Scottish
Borders Council refused to answer questions from retired journalist Bill
Chisholm, but was rebuked by the Information Commissioner
A
BOMBSHELL report about the loss of more than £2.4 million of public money by
Scottish Borders Council casts doubt on the official investigation into that
loss.
Distinguished
journalist Bill Chisholm, who was awarded the MBE for services to journalism
when he retired some years ago, spent 30 months investigating the scandal. The
Easter Langlee waste transfer system was never built but still cost the public
purse more than £2.4m.
Despite
Scottish Borders Council (SBC) constantly refusing to answer his questions,
Chisholm – now 72 and describing himself as a concerned council tax payer –
persevered and the Scottish Information Commissioner ruled in his favour seven
times so that he was able to access the information, which he claims shows
mismanagement and a misuse of public funds.
But
Audit Scotland’s investigation has cleared the council and it says its file on
the matter is now closed.
The
saga began in 2011 when the council awarded a 24-year waste management contract,
valued at between £65m and £80m, to an English firm, New Earth Solutions Group
(NESG), which would include the development and construction of a “cutting-edge”
waste treatment facility at Easter Langlee near Galashiels at an estimated cost
of up to £23m.
Chisholm’s
43-page report alleges the technology to be used at Easter Langlee by
Dorset-based NESG, backed by Isle of Man-based New Earth Recycling &
Renewables [Infrastructure] PLC (NERR), was not fully tried and
tested.
He
reports: “In an interview published in the Journal of the Chartered Institute of
Waste Management in October 2015 … Richard Brooke, the commercial director of
NESG, said ‘The development in Scotland that would have been New Earth’s sixth
facility did not come to fruition for a variety of reasons … the specific energy
technology to be built and operated was not ready to bring on-line on a
commercial scale.’”
The
contractors were given more time and 18 SBC councillors and officers visited
NESG’s premises in October 2014 – a trip that cost council taxpayers almost
£4,000.
NESG
then failed to deliver on Easter Langlee. Less than four months later on 19
February, 2015, the contract was terminated.
Both
NESG and NERR went bust and SBC had to write off more than £2.4m. The council
has since tried to establish its own new £4.8m waste transfer system at Easter
Langlee, but after planning problems work has still not begun and the council
continues to face penalties for its failure to treat its
waste.
Chisholm
asked a series of questions about the technology and funding but received
insufficient answers.
The
Information Commissioner then overruled SBC in very strong terms, saying: “In
the Commissioner’s view, disclosure of the withheld information would serve the
public interest in informing the public about the actions and decisions taken by
the council, the basis for those actions and decisions, and the reasons why the
project failed. The project had involved many years of work, and substantial
sums of public money.”
Chisholm
was finally told by SBC that the costs involved during the lifetime of the
contract totalled £1.968 million – excluding 20 per cent VAT – with much of the
money having gone to highly paid consultants.
After
external auditors KPMG passed the council’s accounts, public spending watchdog
Audit Scotland took over as auditors and concluded the council acted correctly.
Both SBC and Audit Scotland have refused to re-open any inquiry into the failed
project.
Chisholm
told The National: “I would suggest Audit Scotland has made a misjudgment [in
connection] with the Borders’ £65m waste management
contract
“A
significant number of people who have read the report, including an eminent
procurement expert, have expressed the view that there are many issues I have
uncovered which would justify an investigation.
“Examples
include the question of whether the council might have breached EU procurement
rules, not to mention the complete loss of at least £2.4m of taxpayers’
money.”
Chisholm
added: “Audit Scotland may have closed the file on Project Easter Langlee: I
have not.”
A
Scottish Borders Council spokesperson said yesterday: “Mr Chisholm has not yet
presented Scottish Borders Council formally with a copy of his report, however
it is worth noting that both KPMG and Audit Scotland have examined the matter
and are both satisfied with the steps taken by the council in relation to the
contract with New Earth Solutions.”
An
Audit Scotland spokesman said: “In our response to Mr Chisholm we explained that
our opinion is that the council came to a reasonable judgment in terminating the
contract when it did. We are also satisfied that audit work previously completed
by the external auditor showed that the council followed a reasonable process in
the procurement of the waste management contract.”
Thursday, 19 October 2017
The file ignored by Audit Scotland, parliament and politicians [5]
2013’s NOTIFICATION
OF A TWO-YEAR DELAY
The project had been beset by problems and issues from the
very outset thanks to a combination of undeveloped technology and the absence
of the £23 million to pay for it.
Among a collection of 80 reports, emails and other
correspondence which SBC released in August 2017 on the SIC’s orders were
details of yet another delay of two years of which notice was given by NES in
late 2013. The NEAT trials in Canford were going extremely badly, and after a
catalogue of excuses the contractors finally admitted there was no prospect of
commissioning the Borders plant until July 2017 although even that date could
prove to be ‘ambitious’.
Here’s how the council’s own consultants reacted to the news
– although the council seemed content to allow matters to drift on.
SLR Consulting (technical experts) wrote: “In summary it is difficult for SLR to
understand whether there is a reticence to try to develop because; data
attained does not show the process favourably; if operational issues at
Avonmouth are taking priority or are showing some fundamental issues with the
technology; if the technical team are capable of addressing and managing the
problems to an expedient solution.”
And financial advisers Nevin Associates were more forthright
in their correspondence with SBC following the latest test failure at Canford: “This may have been the final incident that
convinced NES to come clean and admit that there was no chance of implementing
NEAT on a commercial scale in 2014.
“This could leave us
hanging on the outcome of the Canford trials, over which we have no control,
and if those were to fail or (more likely) take longer than anticipated to
succeed, then we would still potentially be exposed to the risk of having no
treatment solution in place for the Council’s residual waste.
“It is imperative
that momentum is not lost and that NES show evidence of continued commitment to
the project, otherwise we may have little option but to pursue a Plan B to
avoid the risk that the Council fails to achieve ZWP regulatory requirements.”
NES had already been granted a so-called ‘contract moratorium’
giving them extra time to solve the various problems dogging Project Easter
Langlee.
Surely council members should have stepped in and ordered an
end to the fiasco in December 2013. That would have avoided a 15 month period
up to February 2015 when tens if not hundreds of thousands of pounds of public
money continued to be squandered without any progress being made. But yet again
councillors appear to have been conspicuous by their absence.
CONCLUSION – Those
who take the trouble to read this report are free to draw their own
conclusions.
In my opinion Scottish Borders Council - at the very least -
was grossly incompetent in its stewardship of substantial sums of public money.
SBC was equally inept in the management and administration of a £23 million
building contract, work on which had not even started after almost four years
of dithering and interminable delays caused by a model of technology which had
never been commercially proven, and by an inability to secure funding for
construction.
The fact that no-one will be held to account for the entire
debacle is regrettable and disgraceful.
That concludes our "serialisation" of the comprehensive document which our regulatory bodies and public representatives chose to ignore and refused to act upon. WHY? As we said at the outset your comments will be welcomed.
The file ignored by Audit Scotland, parliament and politicians [4]
MONITORING OF PROJECT BY ELECTED MEMBERS
There is virtually no mention of councillor involvement in the Easter Langlee project in any of the documents SBC has volunteered to give me or in the many more released on the orders of the Scottish Information Commissioner.
There is virtually no mention of councillor involvement in the Easter Langlee project in any of the documents SBC has volunteered to give me or in the many more released on the orders of the Scottish Information Commissioner.
Minutes of meetings should provide a full picture of the
role played by our elected members, but incredibly, during my inquiries I have
been told on more than one occasion that events were not formally recorded.
Therefore written documents containing information about the ill-fated scheme
do not, in many cases, exist on the council’s ‘New Earth Solutions’ file. I
would submit that such an admission of sloppy record keeping should be worthy
of investigation on its own.
A classic example of this cavalier approach towards the
(non) minuting of meetings came to light after I submitted a FOI request
seeking information about the council’s large delegation of elected members and
officers who made a “fact-finding” trip to NESG headquarters at Avonmouth in
October 2014, just four months before the Easter Langlee shipwreck had to be
abandoned.
No fewer than 18 of the most powerful members and officials
of SBC made the trip (including an overnight stay) at a total cost to taxpayers
of £3,939.35. In public statements following their return to the Borders they
made it clear they were pleased with what they had seen and were convinced SBC
was “on the right track”.
When I requested a list of the questions asked and answers
given at a briefing session this is what I was told: “There was then a question and answer session with NES so that Councillors
could get a detailed understanding of the delivery strategy, technology development,
permit and funding. No information is held on record in respect of the
questions or answers provided. Only the presentations are held – which are
commercially confidential, a redacted copy is attached.”
I went on to ask for copies of reports generated before and
after the visit. Here’s the reply from SBC: “Subsequent project reports, minutes and emails make reference to the
visit but were not generated specifically as a consequence of the visit. Again
the content of these documents contains commercially confidential information
and cannot be released.”
This repeated failure to maintain written records which
appears to have permeated much of the four-year liaison between SBC and NESG
may be a convenient way of avoiding public scrutiny. But it also runs totally
counter to the local authority’s own Information Governance Policy.
That document states unequivocally: “Scottish Borders Council is committed to creating, managing and
keeping records that document its principal activities. Information must be
processed and protected diligently, lawfully and ethically through good data
security, accurate information and informed openness.”
One can only assume those high-minded principles ‘went out
of the window’ in the case of the Easter Langlee shambles. Or perhaps the
failed Easter Langlee project is not regarded as one of SBC’s “principal
activities”.
In fact the visit to the Avonmouth facility may well have
been a complete waste of time and money. The misfiring steam technology there was
different from the system which was to have been deployed in Galashiels. The
18-strong team carrying out ‘due diligence’ should, according to some experts,
have been 67 miles from Avonmouth - in Canford - where NEAT was on trial.
Councillor David Parker, the local authority’s leader, told
the Border Telegraph in October 2014
(following the visit) the Avonmouth trip had been “valuable and illuminating”.
“The integrated WTF is a really big deal for our council as
it will transform the way we deal with our waste and help us comply with our
zero waste obligations,” he told the newspaper.
“It also involves a major investment, in partnership with
NES, which requires councillors to carry out due diligence and, in that
respect, the trip was necessary. I am satisfied after our visit that we are on
the right track and confident that the WTF will be up and running before the
2019 contract deadline, hopefully by mid-2017.”
Contrast that upbeat declaration with DUFF & PHELPS
ADMINISTRATORS’ REPORT on New Earth Solutions Group July 2016:
Paragraph 2.8 – “In
October 2014 (the same month in which the Borders delegation was briefed by
NESG) the Group carried approximately
£159 million of debt, with £37 million due to the Banking Group (Co-op) and
£102 million to New Earth Recycling & Renewables [Infrastructure] PLC
(NERR) which was subordinated to the Banking Group’s debt. A further £20
million was also owed to Macquarie Bank with a request for further funding.
Funding from NERR was suspended in 2014 and Co-op was requested to step in to
provide financing.”
In other words the due diligence carried out by Councillor
Parker and his colleagues managed to miss the fact that NESG was completely insolvent
long before the contract was terminated. The cash-strapped company was, to all
intents and purposes, incapable of delivering the Easter Langlee project a year
if not more prior to February 2015. Did anyone examine the company’s books?
What information were the expensive financial consultants [hired at a cost of £146,000]
giving SBC about their contractor’s economic well-being (or lack of it)?
COMING NEXT - 2013’s NOTIFICATION
OF A TWO-YEAR DELAY
The file ignored by Audit Scotland, parliament and politicians [3]
REVELATIONS AND ISSUES THROWN UP BY THE
INVESTIGATION
SBC undoubtedly wished to draw a line in the sand under the
New Earth affair as soon as the highly embarrassing decision to terminate the
useless contract was taken in February 2015. Their attitude towards my series
of FOI requests proves that beyond any reasonable doubt.
But information they have been forced to give me on the
instructions of the SIC has penetrated the wall of silence and has shed some
light on many worrying aspects of the council’s dealings with a group of
financially unstable companies and funds. However, it is impossible to complete
the picture without full disclosure. Here are some of the points requiring full
investigation:
1. NESG TRACK RECORD
AND CONDUCT - NESG was a relatively inexperienced player in the waste
management industry, and had little if any knowledge of environmental rules and
regulations governing waste disposal in Scotland, including SEPA’s rigorous process
before issuing operating certificates.
Information I
obtained showed how NESG became so frustrated over delays in the sanctioning of
a permit for the ATT aspect of the Easter Langlee project that they suggested
SBC and others should put pressure on the independent environmental watchdog to
achieve the desired result. This surely amounted to totally unacceptable and
unprofessional conduct.
2. SURETY FOR SEPA
- In the very early stages of the contract SBC had to provide financial
security in the sum of £315,000 to SEPA on behalf of New Earth Solutions
(Scottish Borders) Ltd., the ‘ special vehicle’ set up to deliver the Borders
project. The council refused to tell me why this was necessary on grounds of
“commercial interests”.
The SIC disagreed and told SBC to give me the information I
had asked for. It transpired that NES could not acquire £315,000 of insurance
without incurring costs which would have had to be passed back to the council “nor can they afford to hold the capital
aside to cover this requirement”. So a contractor involved in a multi-million
pound scheme didn’t have £315,000 to spare. Surely alarm bells should have been
ringing at SBC. Did anyone ask questions about such a worrying issue?
3. THE STATUS OF NERR
& PGIOM - Information obtained during the course of my inquiries has
confirmed that SBC were completely unaware of many complaints lodged by
investors and shareholders in the NERR fund and against its parent company
PGIOM. These businesses were crucial to the successful delivery of Easter
Langlee, and SBC was told £6 million per month was pouring into NERR from eager
‘green’ investors.
The truth was that any money reaching NERR’s coffers was
either being used to prop up NESG (£39 million in total) or being siphoned off
by PGIOM managers and controllers in fees (£12.027 million in 2014 and £10.748
million in 2013 while the Borders contract was ‘live’). The impression is given
that SBC accepted at face value what NESG and NERR were telling them. Even in
the early years of the contract (2011) NESG was recording sizeable financial
losses.
Liquidators Deloitte appointed to investigate NERR by the
Isle of Man Financial Services Authority soon discovered almost 3,500 investors
and shareholders in the fund would get none of their money back. Deloitte is
currently considering the possibility of pursuing third parties in a bid to
recoup cash and NERR has insufficient resources to even pay for its own
liquidation. PGIOM is also in the process of being dissolved. How did SBC
become involved with such unstable offshore entities?
4. DEED OF VARIATION
– Perhaps the most important reason for the collapse of the project, and the
most puzzling issue to emerge from SBC’s web of secrecy. Within a matter of
months of the original contract being signed NESG was telling SBC the MBT plant
was undeliverable because it could not attract bank funding as a stand-alone
project. How much had changed in such a short period of time? Why were MBT
facilities being developed elsewhere in the UK? Did anyone at SBC ask?
In October 2012 members of SBC decided (in private,
naturally) to radically change the terms of their contract with NESG to include
ATT using so-called NEAT Technology, NESG’s very own brand of gasification and pyrolysis
to convert rubbish into electricity.
The councillors must have realised they were taking a huge
gamble. Apparently they were labouring under the impression NEAT could install
them as champions of the Scottish waste disposal league table. But in fact the
technology had not even started its arduous journey through development trials
at NESG’s R&D centre in Canford, Kent.
How was any financial institution likely to put up £23
million under those circumstances? What persuaded SBC’s elected members to
sanction NEAT when the technology was not commercially proven and funding was
not guaranteed? Each member who voted in favour of the DoV must be asked to
explain their reasoning, and officers and members of the Project Team who
recommended this risky course of action also need to provide a detailed public explanation.
In an interview published in the Journal of the Chartered
Institute of Waste Management in October 2015 - AFTER the SBC/NESG contract was shredded, and THREE YEARS AFTER the DoV was rubber-stamped - Richard Brooke, the
commercial director of NES, confirmed that the form of technology which had
been planned for Easter Langlee was not commercially ready in late 2014. So why
did SBC sign up for it in October 2012? Brooke’s reference to the Borders
project reads as follows:
“The development in Scotland that would have been New
Earth’s sixth facility did not come to fruition for a variety of reasons, most
notably the drop-off in the quantity of residual waste requiring treatment; and the specific energy technology to be
built and operated was not ready to bring on-line on a commercial scale.”
This amounts to a damning indictment of SBC’s decision
making. In actual fact this form of ATT technology remains unproven in 2017
while a similar system installed at another NESG facility in Avonmouth, Bristol
has proved so troublesome the entire plant has had to be closed down to allow
radical remedial work to be undertaken. It is hoped to reopen the ATT there in
2018.
COMING NEXT - MONITORING OF PROJECT BY ELECTED MEMBERS